Reservoir Road sewer project delay stirs residents' criticism
Several Reservoir Road residents lambasted Blair Township Water and Sewer Authority engineer Dave Cunningham of Keller Engineers at an authority meeting Wednesday over issues with a sewer project, including a missed a deadline that will keep the authority from using a $2.5 million American Rescue Plan Act grant as initially intended, while putting at risk another $3.8 million Community Development Block Grant for a second phase. The residents demanded an audit of approximately $600,000 the authority has spent on engineering for the project and called for the authority to fire Keller and ...