BEDFORD -- Reviewing Bedford County's five-year capital improvement plan, the commissioners agreed to allocate $600,000 to pressing projects in 2027, including a 911 uninterruptible power supply system and a roof leak on the courthouse's second floor.

Director of Finance Melissa Millard said at Friday's preliminary budget meeting that she wanted a better idea of projects commissioners wanted to address next year, which will be included in its capital improvement plan spanning 2027-31.

Some line items listed on the capital improvement plan included a 911 UPS replacement for $159,350; courthouse dome, louvers and porch repairs for $200,000; 911 recorder upgrade for 36,521; HR badge readers for $96,578; sheriff vehicle for $14,065; jail door control for $20,000; bridge maintenance coordination for $27,000; IT upgrades for mobile management for $2,600; IT upgrades for wireless access-ups backup for $3,475; courthouse roof leak for $25,000; and upgrades for 10 computers for $8,200.

Commissioner Deb Baughman asked Millard how she chose some projects over others while developing next year's preliminary capital improvement plan, to which Millard said she prioritized safety when adding the 911 UPS replacement system and the 911 recorder upgrade.

"I felt that was important because we don't want that to fail or interfere with 911 communications," she said, noting the county isn't in that position yet but eventually will be.

Commissioner JR Winck asked Millard if the emergency management department was going to apply for grant funding for the 911 replacement system.

"Is she going to? Absolutely, but there's just no guarantee we could get that federal DOT grant we're hoping to receive," Millard said, adding she's spoken with many county departments that are searching for grant funding.

Safety concerns also apply to the courthouse dome, louvers and porch repairs, she said. After speaking with Judge Travis Livengood, the plan is to complete upgrades before the courthouse's 2028 anniversary date.

"I believe you have been discussing these potential improvements for several years, and they keep getting put on the back burner," she said.

Looking at the total for the courthouse dome, louvers and porch repairs, Winck said $200,000 is too much and suggested $100,000 instead.

Millard said that total doesn't touch the provided estimate to work on the dome. Baughman asked if Winck believes the county doesn't need $200,000 for the project or if he's trying to get to a zero expenditure.

Two people who provided the estimate said it was high, Winck said, so it's safe to assume they can reduce what's allocated.

Commissioner Chair Mike Stiles suggested meeting Winck halfway and budgeting for $150,000, and Baughman agreed.

"A lot of (dome) preparation has to be done," Stiles said. "I would love to have enough money in the budget to do it all at one time, instead of doing it once and going back and forth."

Considering the roof leak on the courthouse's second floor, Winck asked if the ceiling tile costs $25,000. Stiles said they must fix the roof instead of patching it, as its warranty expires in June.

"We've been patching the roof; you can only patch so long," he said. "At some point in time, you bite the bullet and fix the problem."

Reviewing other line items, the district attorney's request for Karpel, a case management system, was originally included in the list but was removed because the Strategic Management Planning Program grant is covering costs.

Millard said the county's engineers developed the bridge maintenance line item for covered bridges.

Stiles voiced during the meeting that he wanted a jail door control operator upgrade. He said they updated the doors, knowing controls would be next in line.

Other included line items were HR badge reader upgrades, a previously requested project from last year, and one sheriff vehicle instead of two because Millard hoped one would suffice. Three laptops for the county and six laptops requested by the district attorney's office -- plus an additional laptop -- were included in the computer upgrades category. Stiles said it would cost about $820 per PC, equaling $8,200.

The commissioners also reviewed Children and Youth Services' request for more vehicles, but Stiles said the department listed a few cars that gain less than 2,000 miles per month, and three Subarus manufactured in 2025 that gain less than 20,000 miles per month.

He said it's hard to imagine that each vehicle goes out at the same time.

"I know you two don't want them stranded, and for the small amount the county will have to pay if they become in dire straits and need another vehicle next year, we'll find the money somewhere," Baughman said.

And if they apply for grant funding for the dome project, then that alleviates money for another area, Stiles said.

He said 2027's capital improvement plan totaled $592,789 and suggested rounding it to $600,000 if they need to add a vehicle for Children and Youth Services or Tax Assessment.

"This is a plan," Baughman said. "If something else goes, the jail hot water tank goes, and we need to replace it, things could be swapped out. We're not saying this is set in stone; we just need to set a grand total for capital projects."

A flexible capital plan is standard for all municipalities, Millard said, noting that it's like a regular budget.

She said they completed very few capital improvements in 2026 because of a lack of funds, and Stiles said they completed camera upgrades at the jail and the courthouse this year.

"That was stuff that came up which was not planned for," he said.

In other news, the commissioners finished reviewing the rest of the department requests in their 2027 preliminary budget expenditures, including employee benefits.

The commissioners will meet again at 9 a.m. Wednesday, Nov. 25, in room 303.