Trending
Logan Township may gather three years' worth of Community Development Block Grant money to help fund construction of a sewer line that would serve the worst of several remaining areas in the township with malfunctioning septic systems.
The township will receive $188,000 in CDBG money for the current fiscal year, which -- coupled with a total of $300,000 from the two years preceding -- will provide more than half the cost of running a line up Cashman Road, not far from Little Allegheny Reservoir, according to township Planning Director Cassandra Schmick.
The CDBG money totals $488,000, while the total project cost is estimated to be $900,000, according to information from Schmick.
"I think it's an excellent idea," said Supervisors Chairman Jim Patterson, when Schmick outlined the possibility of using the 2021-23 funds for Cashman at a meeting this week.
Twenty-one homes would be served by the 2,000-foot line, which would hook up to an existing line on Old Mill Run Road, according to Schmick.
"There are a lot of malfunctioning (septic) systems (on Cashman) that I'd like to get corrected," said Dave Pozgar, director of the township's Sewer Department.
Engineers working for the township have found seepages from the on-lot systems, he said.
Cashman runs uphill for about a mile and dead ends into the woods, although there is a private dirt road beyond the dead end.
Construction of a line could create opportunities for future development, Patterson said.
Cashman was one of the areas identified as needing help when the township drew up an Act 537 sewer plan under guidelines of the state Department of Environmental Protection about five years ago, Pozgar said.
Other areas in need of help are Spook Hollow Road, Clemson Road, S Curve Road, Homewood Drive, a section of Davis Road and one or two others, Pozgar said.
The township has been whittling down the list, dealing with the worst areas first, Pozgar said.
After Cashman, the lower section of Spook Hollow, nearest the city, may be next, Pozgar said.
The township has applied for a grant to help pay for the rest of the Cashman project, although sewer funds could pay it if the grant application is unsuccessful, according to Pozgar.
The township should hear in September whether grant money is coming, he said.
Construction of the Cashman line could start in the spring, according to Pozgar.
Effluent from the line would go to an Altoona Water Authority plant, according to Schmick.
Running a sewer line up Cashman Road is a good idea, provided it turns out to be affordable, said resident Brenda Clapper.
She isn't worried on her own account, but it wouldn't seem fair if the cost turned out to be too much for some residents, forcing them to move, she said.
The supervisors initially allocated their $120,000 in CDBG funding for 2021 toward housing rehabilitation, according to Schmick.
The township hasn't spent any of that yet, because housing rehabilitation grew too expensive, partly because of lead remediation requirements, she said.
The cost per house went from about $25,000 to about $50,000, she said.
The township initially held off reallocating the money in hopes that the prices would go down, but they haven't, Schmick said.
The supervisors approved the 2022 CDBG funding of $180,000 for the Cashman Road sewer project, she said.
There will be a second public hearing on the 2023 CDBG proposal on Sept. 28, Schmick said.
The supervisors can adopt the 2023 CDBG plan on Oct. 27.
Mirror Staff Writer William Kibler is at 814-949-7038.