PennDOT projects to begin in region

By William Kibler 4 min read
Mirror photo by Patrick Waksmunski PennDOT workers do preliminary work on the Grazierville truss bridge rehabilitation on US 220 Business over Norfolk Southern Railroad near Eighth Street in Snyder Township on Monday afternoon.

HOLLIDAYSBURG -- Bridge projects in Grazierville and on Wopsononock Avenue and resurfacing I-99 from the Pennsylvania Turnpike to the Sproul/Claysburg exit are among the projects PennDOT has on tap for this year.

During the annual transportation outreach session Monday morning, officials with PennDOT's District 9 -- Bedford, Blair, Cambria, Fulton, Huntingdon and Somerset counties -- highlighted projects anticipated to be in construction status this year.

For the six-county region, PennDOT is planning on paving about 85 miles of roadway, repairing or replacing about 76 bridges and seal coating nearly 380 miles of roadway.

Overall, PennDOT will start $130 million in new construction projects this season.

Vince Greenland, activating executive director of District 9, said he gets asked why PennDOT conducts resurfacing and other maintenance projects on highways like I-99, when they seem to be in good condition.

Often, he said, residents will reference less-prominent roads that are clearly in worse condition, and ask why the department doesn't deal with them first.

Roadwork revolves around federal transportation laws, which require states to manage their portions of the National Highway System to achieve the "Lowest Life Cycle Cost" or LLCC, Greenland said.

To maximize the life of an asset, such as a bridge or road, PennDOT prioritizes the assets based on the cost and the condition.

It's about "the right treatment for the right project at the right time," Greenland said.

Rather than worst-first, departments prioritize roads and bridges that would otherwise slip into a less desirable category quickly -- especially those that would slide to "unacceptable," according to a web page explaining the process.

If a bridge is in poor shape, but will remain no worse than that for 10 years, while a bridge in fair condition is on the verge of slipping to poor, the second bridge gets priority.

Conversely, if a third bridge is in poor condition and about to become unacceptable, it has priority over the second bridge -- "not because it's poor, but because it has little remaining life" unless something is done, according to the web page.

The significance of a highway or bridge is considered alongside its condition, according to the web page.

"The more people that use a structure, the more important the structure is," the web page states.

Thus, I-99 is more significant to the local community than a little-used rural road, and the department prioritizes accordingly.

"Every 12 to 15 years we try to hit the higher-types (of assets)," Greenland said. Otherwise, deterioration starts to set in, particularly as a result of truck traffic.

Greenland spoke of several preservation projects on I-99 and Route 22 during Monday's outreach.

Successive preservation projects won't protect an asset forever, but it can double its life, he said.

Projects to begin

Projects beginning this year include the rehabilitation of the Route 4027, Grazierville Truss bridge, expected to cost $3.3 million.

Also beginning this year is the $3.4 million Route 22 resurfacing project from Weller Road to the end of the four-lane roadway in Blair County and the $2.2 million Wopsononock Avenue Bridge Replacement.

Other projects beginning this year include:

– Route 164 resurfacing from Route 2006 to the Blair County Line, Cambria County, $3 million.

– I-70 resurfacing eastbound from Amaranth to Bedford, Fulton County, $30.1 million.

– Route 522 resurfacing from Keystone Road to Mifflin County, Huntingdon County, $4 million.

– Route 30 resurfacing from Route 219 to Route 281, Somerset County, $2.6 million.

– Route 403 resurfacing and slide repair from U.S. 219 to Route 985, Somerset County, $14.5 million.

Projects continuing

Work to resurface I-99 from the turnpike to Sproul in Bedford County, a $9.8 million project, is among the projects continuing, PennDOT said.

Other notable ongoing projects include:

– Route 96 structure replacements, Bedford County, $3.6 million.

– I-70, resurfacing from Breezewood to Fulton County Line, Bedford County, $19.2 million.

– I-70, resurfacing westbound from Amaranth to Bedford, Fulton County, $19.9 million.

– Route 271 resurfacing from Woodmont Road to Route 3037, Cambria County, $7.1 million.

– Route 22 interchanges resurfacing from Munster to Ebensburg, Cambria County, $7.6 million.

– Route 641 bridge replacements, Huntingdon County, $2.2 million.